Data Center Electricity Bills Would Carry Their Own Transmission Costs Under Texas SB 33, a 2027 Bill Filed November 9
Texas SB 33 would move transmission costs attributable to data centers and other computational load sites into a rate class of their own, with PUCT rules due September 1, 2028. It was filed November 9, 2026 for the session that opens January 12, 2027, and it is not law.
On November 9, 2026, the first day of bill prefiling for the 2027 session, State Sen. Judith Zaffirini filed Senate Bill 33, which would require the Public Utility Commission of Texas (PUCT) to move transmission costs attributable to data centers and other computational load sites into a separate rate class made up only of those customers. PUCT rules would be due by September 1, 2028. SB 33 is a filed bill, not law, and it sets no rate. For Texas commercial electricity buyers it matters because data center electricity bills and small business delivery charges draw on the same ERCOT transmission cost pool today.
Key takeaways
- SB 33 was filed November 9, 2026 for the session that convenes January 12, 2027. As of November 14, 2026 it has no committee referral and is not law.
- The bill would put transmission costs of service attributable to computational load sites, such as data centers, in a rate class composed only of those customers, and it sets no megawatt threshold.
- If it passes, it takes effect September 1, 2027 without a two-thirds vote, and PUCT rules are due by September 1, 2028.
- Separately, PUCT Project 58000 proposes replacing the 4CP transmission allocation method with 12CP. No rule had been adopted as of November 14, 2026.
- For a commercial account, the contract decides exposure: check whether TDU delivery charges are fixed or passed through at cost.
What Happened
Senate Bill 33 was received by the Secretary of the Senate on November 9, 2026, for the regular session of the 90th Texas Legislature, which convenes January 12, 2027. Its caption reads "relating to the recovery of costs related to providing electricity service to customers at a computational load site." As of November 14, 2026, the bill history on Texas Legislature Online shows only the filing and its receipt, with no committee referral yet.
The bill moves two existing subsections of Section 35.004 of the Texas Utilities Code into a new Section 35.0041 and adds four more. The carried-over part is not new. Subsections (a) and (b) restate the requirement, added by Section 1 of Senate Bill 6 in 2025, that a large load subject to the interconnection standards in Section 37.0561 contribute to its utility's cost of interconnecting it. We covered the PUCT and ERCOT follow-up to that law in our briefing on the July 17 SB 6 memorandum.
The new part is subsection (c). It covers costs not recovered under (a) or (b), and it applies "notwithstanding Section 35.004," the provision under which ERCOT transmission service is priced today. Under it, the PUCT "by rule shall establish a system" to:
- "ensure that transmission costs of service attributable to a customer receiving electricity service at a computational load site are allocated to a separate transmission cost of service rate class composed only of that type of customer," and
- "require each electric utility that provides distribution service to a customer described by this subsection to use a rate mechanism established by the commission" for that purpose.
Subsection (d) defines a computational load site as one or more buildings, structures or installations at a single location that "primarily contains information technology infrastructure" used for creating, executing and delivering software applications and services, artificial intelligence training, deployment and delivery, adding virtual currency transactions to a distributed ledger, or "other computational activities at a data center." The site must also be one that "is supplied through electrical equipment that is connected to the bulk power system." The definition sets no megawatt threshold. Subsection (f) says the system may require those customers to "pay minimum demand charges, operate under contract terms specified by the commission," or meet other requirements the PUCT finds necessary "to ensure that transmission costs of service attributable to those customers are not paid by other customers."
Two dates follow. Section 2 gives the PUCT until September 1, 2028 to adopt or revise its rules. Section 3 makes the bill effective immediately if it receives a two-thirds vote of all members elected to each chamber, and otherwise on September 1, 2027. Read the introduced text of SB 33 and its bill history.
How are transmission costs allocated in ERCOT today?
ERCOT transmission costs are pooled statewide and shared by summer peak load. Under PUCT rule 16 TAC 25.192, each transmission owner's annual wholesale rate equals its PUCT-approved transmission cost of service divided by the average of ERCOT's coincident peak demand in June, July, August and September, known as 4CP. Every distribution utility then pays that rate on its own prior-year 4CP load. A new data center adds to its utility's 4CP share the same way any other load does. The utility then spreads its wholesale transmission bill across its retail rate classes through base delivery rates and its transmission cost recovery factor (TCRF), which updates by default on March 1 and September 1 under 16 TAC 25.193.
Is the PUCT already changing the formula?
The PUCT is already reviewing the formula, on a separate track from SB 33. Project 58000 is the commission's rulemaking to update wholesale and investor-owned utility retail transmission cost recovery in the ERCOT region, and it follows the 4CP review that Section 6 of Senate Bill 6 ordered. At its July 9, 2026 open meeting, the commission approved a proposal for publication that would replace the 4CP method with a 12 coincident peak (12CP) method for assigning transmission costs. The proposal would also add a new rule, 16 TAC 25.252, setting tariff terms for service to large load customers.
Comments were due August 11, 2026. Filers range from the Data Center Coalition, ERCOT, the Office of Public Utility Counsel and Texas Industrial Energy Consumers to Oncor, CenterPoint, the AEP companies, TNMP and the Texas REP Coalition. As of November 14, 2026, the Project 58000 filing list shows 70 filings and no adoption order. SB 33 does not mention Project 58000, and its text does not say how a statutory rate class would fit with whatever rule the commission adopts.
What other data center electricity bills are filed?
SB 33 is one of several electricity bills filed in the first week of prefiling. By caption, the ones closest to data center and large load policy are:
- SB 32 (Zaffirini): a PUCT permit to construct a large computational load site, with an administrative penalty.
- SB 34 (Zaffirini): county authority to regulate the development of certain large electricity users.
- SB 338 (Perry and others): a bill "relating to data centers," filed November 12.
- HB 547 (Bhojani): county noise study requirements and site construction approval for facilities operated by certain large load customers.
- HB 589 (Lalani): Texas Energy Fund loans and grants for certain electric generating facilities.
- HB 184 (Slawson): a PUCT study of constructing certain extra high voltage transmission lines.
- SB 191 (Hall): interconnection of an ERCOT-region facility to certain other facilities.
Those one-line descriptions come from each bill's caption on the Legislature's Utilities, Electric subject index, not from a reading of each bill's text.
Which dates matter for SB 33?
Seven dates frame SB 33 and the rulemaking beside it, and only the first three have already happened.
| Date | Event | Status as of Nov 14, 2026 |
|---|---|---|
| July 9, 2026 | PUCT approves the Project 58000 proposal (4CP to 12CP, new 16 TAC 25.252) | Proposed, no adoption order |
| Aug 11, 2026 | Project 58000 comment deadline | Passed |
| Nov 9, 2026 | SB 33 filed | Filed, no committee referral |
| Jan 12, 2027 | 90th Legislature convenes | Scheduled |
| Mar 1, 2027 | Default TCRF update date under 16 TAC 25.193 | Scheduled |
| Sept 1, 2027 | SB 33 takes effect without a two-thirds vote, if passed | Contingent |
| Sept 1, 2028 | Deadline for PUCT rules under SB 33, if passed | Contingent |
Sources: SB 33 introduced text and history, PUCT Project 58000 filings, 16 TAC 25.193.
Impact on Commercial Electricity Buyers in Texas
SB 33 changes nothing on a business electricity bill this year and may never become law, but it targets the exact line where data center growth and commercial delivery charges meet: transmission cost of service. We see three channels where the bill, or the Project 58000 rule running beside it, could reach a commercial account. None of them tells you whether your delivery charges would rise or fall, because the bill directs how costs are allocated, not how large they are.
The transmission path to your bill. Transmission reaches a commercial bill through your TDU's delivery charges, partly in base rates and partly in the TCRF. Under the current method, a new large load adds to its utility's 4CP share and the utility spreads the resulting cost across its retail classes. SB 33 would pull the transmission costs "attributable to" computational load site customers into a class of their own, and the PUCT rule would decide how "attributable" is measured. Our November 4 briefing on CenterPoint's capital plan and the TCRF shows how one utility's transmission build spreads across ERCOT. Our October 15 briefing on the large load interconnection rule covers the separate question of who pays to connect a large site.
Fixed or passed-through delivery charges. Whether a reallocation reaches your account mid-contract depends on how your quote treats TDU charges. Some commercial offers build delivery charges into a fixed price, often with a clause for regulatory changes, and others pass TDU charges through at cost, so an approved change flows to your bill at the next update. Your contract and Electricity Facts Label say which one you have, and our guide to reading a commercial Electricity Facts Label shows where that language sits.
Contract timing. A 24 or 36 month term signed this month runs past both September 1, 2027, the effective date without a two-thirds vote, and September 1, 2028, the rule deadline. The average term across the published commercial offers we track was 24.4 months as of our November 9 weekly report, which also covered the session calendar and the governor-elect's data center pledge. A term that long also crosses several TCRF updates on the default March 1 and September 1 schedule.
The Rate Class Test: Three Checks Before a 2027 Bill Reaches Your Delivery Charges
Before you sign or renew a commercial contract that runs into 2028, put it through the three checks we use to read a cost-allocation bill like SB 33, so a headline about data centers neither talks you out of a sound fixed rate nor leaves a pass-through clause unread.
1. Which rate class is your meter in today?
Your bill or your TDU's tariff names your class, for example CenterPoint's secondary service at 10 kVA or less, secondary over 10 kVA, primary and transmission classes. The class sets how you pay transmission costs: per kWh for the smallest accounts and per unit of demand for larger ones. SB 33 would add a class only for computational load site customers, so the first question is whether your site could meet that definition at all.
2. Does your contract fix or pass through TDU charges?
Find the delivery charge language in your contract and Electricity Facts Label. If TDU charges pass through at cost, a PUCT-approved rate change reaches you at the next update. If they are fixed, read the change-in-law or regulatory clause to see what can still move.
3. Does your term end before or after September 1, 2028?
That is the latest date SB 33 gives the PUCT to adopt rules, if the bill passes. A term that ends earlier renews into whatever rule exists at that point. A term that runs past it carries whatever your contract says about mid-term regulatory changes.
What You Should Do
Most commercial accounts can work through these five steps in under an hour, and none of them depends on whether SB 33 passes, because the same steps cover the scheduled TCRF updates and any rule the PUCT adopts in Project 58000.
- Find your TDU and rate class on a recent bill, and note whether your transmission charge is billed per kWh or per unit of demand.
- Pull your contract and Electricity Facts Label and mark whether TDU delivery charges are fixed or passed through at cost.
- Write down your term end date and compare it with September 1, 2027 and September 1, 2028.
- If you are quoting a renewal now, ask for 12, 24 and 36 month offers on the same day, with the TDU treatment stated in writing for each.
- Watch SB 33 on Texas Legislature Online for a committee referral after the session opens January 12, 2027, and the Project 58000 filing list for an adoption order.
Questions to Ask Your REP or Broker
These four questions pin down how a quote handles a transmission cost change, which rarely shows up on a rate comparison but decides whether a 2027 bill or a PUCT rule reaches your account before renewal.
- Are TDU delivery charges in this quote fixed for the term or passed through at cost?
- If the PUCT creates a new transmission rate class or replaces the 4CP method during the term, can this price change?
- Does the contract's change-in-law clause cover a statute that takes effect September 1, 2027?
- How will the March 1 and September 1 TCRF updates show up on the bill during this term?
Subscribe to Weekly Market Insights, free. We publish a data-driven rate report every Monday, and we will note a committee referral or hearing for SB 33 there.
To compare offers for your meter, see every commercial plan we track in our data download.
For the full picture, see our guide to commercial electricity rates in Texas.
Frequently Asked Questions
What does Texas SB 33 do?
Texas SB 33, filed November 9, 2026, would require the Public Utility Commission of Texas to allocate transmission costs of service attributable to customers at a computational load site, such as a data center, to a separate rate class made up only of those customers. It also lets the PUCT require minimum demand charges and contract terms so those costs are not paid by other customers.
Is SB 33 law yet?
No. As of November 14, 2026, SB 33 has only been filed, and the 90th Legislature convenes January 12, 2027. If it passes, it takes effect immediately with a two-thirds vote of each chamber, or otherwise on September 1, 2027, and the PUCT would have until September 1, 2028 to adopt rules.
Does SB 33 cover a small business with a server room?
SB 33 defines a computational load site as one or more buildings, structures or installations at a single location that "primarily contains" information technology infrastructure for software, artificial intelligence, virtual currency or other data center computing, supplied through equipment connected to the bulk power system. The test in the text is what the site primarily contains, not whether it has servers. The bill sets no megawatt threshold, so the PUCT rule would set how the definition applies.
Would SB 33 lower delivery charges for small businesses?
SB 33 sets no rate and does not predict a change in anyone's delivery charges. It directs how transmission costs attributable to computational load sites are allocated, and any effect on other rate classes would depend on rules the PUCT would have until September 1, 2028 to write. Your contract's TDU terms decide whether a change reaches you before renewal.