Large Load Tariff Terms Reach PUCT's Draft Standard Agreement for 75 MW Hookups, and the Costs Run Through the Same Filings as Your Delivery Charges
The PUCT's proposed standard large load interconnection agreement, approved for publication November 5, 2026, has utilities report a 75 MW hookup's costs in the same proceedings that set business delivery charges. Comments are due December 14, and the filings do not say how much reaches small accounts.
On November 5, 2026, the Public Utility Commission of Texas (PUCT) approved for publication a proposed standard large load interconnection agreement (SLLIA) for every ERCOT site of 75 MW or more, with comments due December 14, 2026. The draft writes in the terms of Texas's pending large load tariff rule, new 16 TAC 25.252, and it has each utility report its share of a hookup's costs in the same rate proceedings that set the delivery charges on a business electricity bill. The filings do not say how much of that cost, if any, reaches small commercial accounts.
Key takeaways
- The PUCT approved the proposed SLLIA for publication on November 5, 2026 in Project No. 59999. Comments and public hearing requests are due December 14, 2026.
- The agreement would govern every large load interconnecting in the ERCOT region. Under 16 TAC 25.194, that is a new or expanded single site at 75 MW or more.
- Proposed Section 6.4 has each utility report its share of interconnection costs in a DCRF or TCOS proceeding, reconcile them in its next base rate case, and report the large load minimum billing demand in a TCRF proceeding.
- The minimum billing demand and the large load tariff terms come from Project 58000, which showed 70 filings and no adoption order on November 19, 2026, so every term in the draft is "subject to change upon adoption."
- Neither the request for comments nor the draft agreement says how much of any large load cost reaches small business delivery charges, or in which direction.
What Happened
The PUCT approved the proposed agreement for publication at its November 5, 2026 open meeting, as Agenda Item No. 40 in Project No. 59999, "Rulemaking to Adopt a Standard Large Load Interconnection Agreement." The commission filed a nine-page request for comments and the staff-recommended draft the same day, and the Texas Register acknowledged the proposal for its November 20, 2026 issue.
The request for comments says the new form "will serve as the standard agreement for all large loads interconnecting within the ERCOT region of Texas and continue the implementation of Senate Bill (SB) 6 enacted in the 89th Legislature (R.S.)." It notes that SB 6 requires the commission to ensure large load customers subject to the PURA 37.0561 standards "contribute to the recovery of costs associated with interconnecting the large load to the utility's system," citing PURA 35.004(c-1), and that the standards be set "in a manner designed to support business development while minimizing the potential for stranded infrastructure costs and maintaining system reliability."
The draft also reaches into a second rulemaking. The SLLIA "will also integrate the transmission cost recovery standards for large load customers pending in Project 58000, including any obligations associated with the 'minimum billing demand,'" and it will incorporate the amendments to 16 TAC 25.192 and 25.193 "and new 25.252 relating to Large Load Customer Tariffs upon adoption of those rules by the commission." It also reflects ERCOT's large load interconnection changes under PGRR 145. The request is plain about what that means for every term: "The contents of the standard agreement are subject to change upon adoption to reflect the final rule text in Project 58000 and any policy decisions reached by the commission in that project."
The request's first question for comment is the only pass-through language in it, and it runs toward the large load, not other customers. It asks how to write in PURA 35.004(c-2), under which an electric cooperative or municipally owned utility that has not adopted customer choice "shall pass through to a large load customer" the reasonable costs to interconnect it. Other questions ask whether to prohibit assignment of the agreement, how the minimum billing demand and its security transfer on assignment, whether a utility must build facilities for a large load that co-locates with generation, and how to set points of interconnection, delivery and metering.
As of November 19, 2026, the Project 59999 filing list shows 10 filings, including a November 10 notice of participation from the Office of Public Utility Counsel (OPUC), the state agency that represents residential and small commercial consumers before the PUCT. Read the primary sources: the request for comments on the SLLIA, the proposed SLLIA, the November 5 PUCT memo setting the December 14 deadline, and the large load interconnection rule, 16 TAC 25.194.
What is a large load tariff in Texas?
A large load tariff in Texas is the set of terms that the PUCT's proposed new rule, 16 TAC 25.252, "Large Load Customer Tariffs," would require transmission utilities and investor-owned distribution utilities to include in the tariffs that govern service to large load customers. The commission proposed it in Project 58000 alongside amendments to 16 TAC 25.192 and 25.193, approved the proposal for publication at its July 9, 2026 open meeting, and printed it in the July 24, 2026 Texas Register.
The same proposal would require a minimum billing demand for large load customers, which the proposed 25.192 defines as "the minimum transmission billing demand associated with large load customers." It would start a large load's billing "at the level of available service at the time it is available," whether or not the site has energized, and it would require each investor-owned distribution utility to file an annual report of the revenue it collects from each customer class. As proposed, the minimum billing demand would be fixed for 20 years, and the commission asked whether it should instead be phased down or extended. The Project 58000 filing list showed 70 filings and no adoption order on November 19, 2026. Our November 16 weekly report covered the 4CP to 12CP change in the same project.
Who counts as a large load?
A large load, for the agreement, is a site that meets "the demand threshold specified by 16 TAC 25.194 in effect at the time the Agreement is executed, whether at transmission voltage or distribution voltage." Under 25.194, in effect since October 8, 2026, that means a site not energized by that date that seeks a new interconnection of 75 MW or more, an expansion that reaches 75 MW for the first time, an expansion of 75 MW or more at a site already above 75 MW, or co-location with a generation resource. Our October 15 briefing on the large load interconnection rule covers its $100,000 study fee and $50,000 per MW of security.
Where would the interconnection costs go?
Section 6.4 of the proposed SLLIA names the proceedings. Section 6.4.A reads: "Unless otherwise ordered by the PUCT or required by PURA, the PUCT Rules, or other applicable law, each applicable Utility Party must (i) report the portion of the interconnection for which they are responsible in a DCRF or TCOS proceeding, as may be applicable for all Direct Interconnection Costs, costs for System Upgrades, and all other cost categories. (ii) reconcile all interconnection costs under this Agreement in its next comprehensive base rate proceeding."
In plain terms, each utility would report its share of a large load's hookup costs in a distribution rider case or a transmission rate case, then reconcile all of the agreement's interconnection costs in its next full rate case.
Section 6.4.B covers the minimum billing demand. It "must be reported in a TCRF proceeding and recovered in the manner required by 16 TAC 25.252," and it must also be reported to ERCOT "on or before the 5th calendar day of each month."
The customer side sits in Section 9. A large load "must pay the large load minimum billing demand described by 16 TAC 25.193 or its successor for the set period of time described in 25.193," and that minimum "is prohibited from being reduced in the event that the Customer's Contracted Peak Demand is decreased," whether ERCOT reallocates the capacity or the customer withdraws it. On top of the primary security that 25.194 sets at the greater of "$50,000 per MW of the contracted peak demand" or the customer's allocated system upgrade costs, the draft adds a separate "Minimum Billing Demand Security." It is posted "at the time transmission capacity is made available to serve the Large Load," "calculated using the formula specified in Exhibit I," and provided "in the form of a letter of credit." A utility may take the customer's contribution in aid of construction (CIAC) in installments, or it "may require the full amount of the CIAC to be paid upon execution of this Agreement."
What do DCRF, TCOS and TCRF mean on a business bill?
DCRF, TCOS and TCRF are the three rate proceedings Section 6.4 names, and each one feeds a line or a component of a Texas business delivery bill. The table lines them up with what the draft agreement would report in each one.
| Proceeding | What it sets | Where it shows up on a business bill | What the proposed SLLIA reports there |
|---|---|---|---|
| DCRF (distribution cost recovery factor) | A rider that updates distribution charges between base rate cases | The DCRF line inside TDU delivery charges | The utility's share of interconnection costs, where applicable (6.4.A(i)) |
| TCOS (transmission cost of service) | A transmission utility's wholesale transmission rate under 16 TAC 25.192 | Indirectly, through the TCRF and base delivery rates | The utility's share of interconnection costs, where applicable (6.4.A(i)) |
| Comprehensive base rate case | Base delivery rates for each customer class | Base delivery charges per kWh or per kW | A reconciliation of all interconnection costs under the agreement (6.4.A(ii)) |
| TCRF (transmission cost recovery factor) | A rider that passes wholesale transmission costs to retail classes under 16 TAC 25.193 | The TCRF line inside TDU delivery charges | The large load minimum billing demand (6.4.B) |
Sources: proposed SLLIA Sections 6.4.A and 6.4.B (PUCT Project No. 59999, Item 5), 16 TAC 25.192 and 16 TAC 25.193.
Which dates matter for the large load agreement?
These are the dates behind the agreement and the rule it depends on. The next fixed one is December 14, and the date that decides the final terms, the Project 58000 adoption, has not been set.
| Date | Event | Status as of Nov 19, 2026 |
|---|---|---|
| July 9, 2026 | PUCT approves the Project 58000 proposal (12CP, minimum billing demand, new 16 TAC 25.252) | Proposed, no adoption order |
| July 24, 2026 | Project 58000 proposal printed in the Texas Register | Published |
| Aug 11, 2026 | Project 58000 comment deadline | Passed |
| Oct 8, 2026 | 16 TAC 25.194 takes effect | In effect |
| Nov 5, 2026 | PUCT approves the proposed SLLIA for publication | Comments open |
| Nov 10, 2026 | OPUC files notice of participation in Project 59999 | Filed |
| Nov 20, 2026 | Texas Register issue for the SLLIA proposal | Scheduled |
| Dec 14, 2026 | SLLIA comment and public hearing request deadline | Open |
| Not set | Project 58000 adoption | Pending |
Sources: PUCT Project No. 59999 and Project No. 58000 filing lists, the Project 59999 request for comments, 16 TAC 25.194.
Impact on Commercial Electricity Buyers in Texas
The draft agreement changes nothing on a small business bill today, and the filings do not say whether any large load cost will raise or lower small commercial delivery charges. What the draft does fix is the route: each utility's share of a 75 MW hookup, and the large load minimum billing demand, would be reported in the same proceedings that set three parts of your delivery charges. We see three channels, and none of them comes with a number yet.
Delivery riders. DCRF and TCRF are riders, and riders reset on their own schedules between base rate cases. On November 1, 2026, small business meters paid 1.29 to 5.38 cents per kWh in delivery depending on the TDU, and riders made up about 38 to 77 percent of those per-kWh charges, as our guide to TDU delivery charges for Texas business accounts shows. A rider proceeding is where a utility's large load figures would be filed and examined under the draft. Our November 4 briefing on CenterPoint's capital plan and the TCRF shows how one utility's transmission costs spread across ERCOT.
The next base rate case. Section 6.4.A(ii) has each utility reconcile all interconnection costs under the agreement in its next comprehensive base rate proceeding. That is the same case that sets base delivery rates for each customer class, small commercial classes included. The draft does not say how that reconciliation would come out for any class.
Your contract terms. Whether a rider or base rate change reaches you mid-term depends on your contract. Under 16 TAC 25.475(b)(5), a fixed-rate small commercial plan can still change price for actual changes in TDU charges, and under 16 TAC 25.479(g)(2) a REP cannot bill more than the TDU tariff amount, as our TDU guide explains. Our TxCP Commercial Rate Index (TCRI) stood at 6.79 cents per kWh on November 16, 2026, but the SLLIA works on the regulated delivery side of the bill, which REPs pass through and cannot set. The average term across the published commercial offers we track was 24.7 months in that week's report, so a contract signed this month runs well into 2028, and neither project shows an adoption order on its filing list.
On the legislative track, SB 33, filed November 9, would put data center transmission costs in a rate class of their own, as our SB 33 briefing covered. It is a filed bill, not law, and the draft agreement does not mention it.
The Delivery Docket Trace: Three Checks Before a Large Load Filing Reaches Your Bill
Before you sign or renew a commercial contract that runs into 2028, trace a large load filing the way the draft agreement routes it, so a data center headline neither rushes you into a renewal nor leaves a pass-through clause unread.
1. Which TDU and rate class is your meter in?
Your bill names your TDU and your rate class. The class sets how you pay delivery: mainly per kWh below your TDU's demand cutoff and mainly per kW above it. The cutoffs are 10 kW for Oncor and AEP Texas, 10 kVA for CenterPoint and 5 kW for TNMP.
2. Which riders are on your bill, and when do they reset?
Look for DCRF and TCRF lines, or ask your REP for the TDU charges behind an all-in price. Those are the riders whose proceedings Section 6.4 names. Each resets on its own calendar, and the TCRF updates by default on March 1 and September 1 under 16 TAC 25.193.
3. Does your contract fix or pass through TDU charges?
If TDU charges pass through at cost, an approved rider or base rate change reaches you at the next update. If they are fixed, read the regulatory change clause to see what can still move during the term.
What You Should Do
None of these five steps depends on how the commission rules on the draft agreement, because the same moves cover every rider update and base rate case your TDU files, whatever a large load ends up paying.
- Find your TDU and rate class on a recent bill, and note whether delivery is billed per kWh or per kW.
- Pull your contract and Electricity Facts Label and mark whether TDU delivery charges are fixed or passed through at cost.
- Write down your term end date, and note each March 1 and September 1 TCRF update that falls inside it.
- If you are quoting a renewal now, ask for 12, 24 and 36 month offers on the same day, with the TDU treatment stated in writing for each.
- If you want your view on the record, file comments in Project No. 59999 through the PUCT's Interchange by December 14, 2026, and watch the Project 58000 filing list for an adoption order.
Questions to Ask Your REP or Broker
These four questions pin down how a quote treats a delivery charge change, which a rate comparison rarely shows but which decides whether a rider update or a base rate case reaches your account before renewal.
- Are TDU delivery charges in this quote fixed for the term or passed through at cost?
- If the TDU's DCRF or TCRF changes during the term, when does the change show up on the bill?
- If the TDU files a base rate case during the term, can this price change?
- Does the contract's regulatory change clause cover a new PUCT rule, such as the large load tariff rule pending in Project 58000?
Subscribe to Weekly Market Insights, free. We publish a data-driven rate report every Monday, and we will note a Project 58000 adoption order there.
To compare offers for your meter, see every commercial plan we track in our data download.
For the full picture, see the Texas commercial rates by TDU, or our guide to the average commercial electricity price per kWh in Texas.
Frequently Asked Questions
What is a large load tariff in Texas?
A large load tariff in Texas is the set of terms that proposed new rule 16 TAC 25.252, "Large Load Customer Tariffs," would require transmission utilities and investor-owned distribution utilities to include in the tariffs that govern service to large load customers. The PUCT proposed it in Project 58000 in July 2026, and as of November 19, 2026 it had not been adopted.
When are comments due on the standard large load interconnection agreement?
Comments on the proposed standard large load interconnection agreement are due December 14, 2026, and must be filed in PUCT Project No. 59999. A request for a public hearing must also be received by December 14, 2026. The commission approved the draft for publication on November 5, 2026.
Will data center hookups raise small business delivery charges?
The filings do not say. The proposed agreement has each utility report its share of a large load's interconnection costs in a DCRF or TCOS proceeding, reconcile them in its next base rate case, and report the large load minimum billing demand in a TCRF proceeding, but neither the draft nor the request for comments estimates how much reaches any customer class or in which direction.
Who counts as a large load in Texas?
Under 16 TAC 25.194, in effect since October 8, 2026, a large load is an ERCOT site not energized by that date that seeks a new interconnection of 75 MW or more, an expansion reaching 75 MW for the first time, an expansion of 75 MW or more at a site already above 75 MW, or co-location with a generation resource.